|
|
|
 |
 |
|
Tying foundation rebar.
|
Setting stemwall forms. |
 |
 |
|
Vertical 5/8-inch post-tension all-thread rods will transfer roof forces down into foundations reinforced with horizontal #5 rebar.
|
After forms and rebar are in place, concrete stemwalls are poured.
|
 |
 |
|
Pouring concrete stemwall at 4.5-inch slump, and vibrating concrete
to drive out air and level surface.
|
Leveling concrete stemwall by puddling with wood float. |
 |
 |
|
Partially stripped stemwall. Note 6-inch corner-forms at t-intersection.
|
Stripped stemwall with block-down for door-opening, and vertical conduit to bring UF electric cables from under floor up into wall. |
 |
 |
|
Main electrical riser with naked copper U-fer ground bonded to 20-foot length of rebar in footing.
|
Stripped stemwall at south wall. |
 |
 |
|
Installation of electrical boxes with UF direct-burial cable and direct-burial telephone cable into first setting of wall forms.
|
For each 1,000 pounds of dirt, one 94-lb. bag of Portland cement is added. |
 |
 |
| Dry-mixing dirt with Portland cement. |
Adding water to dry-mix. |
 |
 |
| Tamping dirt. |
Tamper. |
 |
 |
|
Dirt tamped to 4 feet. Note sloped top for water drainage in event of rain during construction.
|
Tamped to 4 feet around block-out for tankless water heater. |
 |
 |
|
Set forms to 8 feet. Note: block-out puts water heater to outside of wall, eliminating need for vent-pipe through roof.
|
Walls formed to 8 feet. Note: Forms left off of door opening, allowing access into building. |
 |
|
|
Bobcat pouring dirt into forms set to 8 feet high.
|
|
 |
 |
| Removing wedge bolts. |
4’x’4 form panel is rolled like a square wheel, (it’s 85 pounds!). |
 |
 |
|
| Removing 2’x 4’ form panels. |
Wire panel tie loop ends will be snapped off. Note; pre wired electrical boxes. |
|